Onsite Quick Material Calculations with civil engineering Coefficients

Material Coefficients



Sl no DESCRIPTION UOM  Cement  (Bags) Sand (Cum) Aggregates (Cum) Bricks / Blocks (Nos)
1 RMC M-7.5 Site mix  Cum          3.367           0.468 0.94
2 RMC M-10 Site mix  Cum          4.378           0.456 0.91
3 RMC M-15 Site mix  Cum          6.254           0.434 0.87
4 RMC M-20 Site mix  Cum          7.959           0.415 0.83
5 RMC M-25 Site mix  Cum        10.944           0.380 0.76
6 8" Solid Block Work with CM 1:6 Sqm          0.096           0.021 12.50
7 6" Solid Block Work with CM 1:6 Sqm          0.072           0.016 12.50
8 4" Solid Block Work with CM 1:6 Sqm          0.048           0.011 12.50
9 230mm Brick Work with CM 1:6 Sqm          0.262           0.058 57.97
10 115mm Brick Work with CM 1:6 Sqm          0.131           0.029 57.97
11 Brickwork in Cum Cum          1.440           0.250 504.10
12 Cement Slurry for columns,Beams (1:3 mix, 5mm thk) Sqm          0.045           0.005
13 Internal Ceiling Plastering 12mm thk in CM 1:4 Sqm          0.104           0.015
14 Internal Wall plastering 15mm thk in CM 1:6 Sqm          0.096           0.021
15 External Wall Plastering Sponge finish 20mm in 2 layers: 1st coat 12mm in CM 1:4 and top coat 8mm in CM 1:6 with water proof chemical Sqm          0.149           0.028
16 Mesh for internal/external  wall plastering Sqm          0.017           0.001


Shuttering Runner Coefficients  
Retaining Wall Coefficient
S. No Runner Co efficient
1 4 x 2 0.04 cum
2 4 x 4  -
3 6 x 4 -
Beam Coefficient
S. No Runner Co efficient
1 4 x 2 0.05                         cum
2 4 x 4 0.06                         cum
3 6 x 4 0.03                         cum
Slab Coefficient
S. No Runner Co efficient
1 4 x 2 0.06                   cum  
2 4 x 4 -
3 6 x 4 0.44                   cum
 CEMENT CO-EFFICIENTS
 S/N   DESCRIPTION   UNIT   CO-EF 
 CONCRETE 
     1  P.C.C.1:4:8 below foundation/floors   CUM          3.30
     2  R.C.C. M-25 footing    CUM          7.50
     3  RCC M20 for Roof slab/beam, columns,&stair case   CUM          6.80
     4  DPC 1:3:6   CUM          4.50
 MASONRY WORKS 
     5  SSM for foundation/basement   CUM          1.60
     6  200 mm Solid block   SQM          0.18
     7  100 mm  Solid Block    SQM          0.12
     8  150 mm  Solid Block    SQM          0.15
     9  230 mm Brick Masonry   Cmt          1.40
 PLASTERING 
  10  Ceiling plastering   SQM          0.13
  11  Internal wall plastering   SQM          0.12
  12  Rough plaster in walls(Dadoback)   SQM          0.12
  13  External plastering   SQM          0.20
  14  Basement waterproof plastering    SQM          0.18
 STAIRCASE WORKS 
  15  Tread-Multicolour-20mm  thk.   SQM          0.22
  16  Riser-Multicolour-20mm thk.   SQM          0.22
  17  Tread-Sadaralli -10mm thk.   SQM          0.22
  18  Riser-Sadaralli -10mm thk.   SQM          0.22
 FLOORING 
  19  Screed concrete    SQM          0.40
  20  Multicolour  granite 20 mm   SQM          0.22
  21  Multicolour  granite 10 mm   SQM          0.22
  22  Sadaralli granite   SQM          0.22
  23  Vitrified tile flooring (Labour only)   SQM          0.22
  24  Cudappa slab flooring   SQM          0.22
  25  Eurocon Tiles for ramp   SQM          0.22
  26  Broken  tile  flooring   SQM          0.30
 WALL TILING 
  27  Toilets & Pantry   SQM          0.22
  28  Ceramic tile dadoing (Plasma gold)   SQM          0.22
  29  Ceramic tile dadoing (Karara grey)   SQM          0.22
  30  Multi colour Wall Dado 20 mm thick   SQM          0.22
  31  Jet Black Wall Dado 20mm thick   SQM          0.22
 SKIRTING 
  32  Granite tile-Multi colour   Rm        0.025
  33  Sadralli granite   Rm        0.025
  34  Vitrified  tile-glossy(Labour only)   Rm        0.025
  35  Cudappah slab skirting   Rm        0.025
  36  Cement  skirting   Rm        0.030
 MISCELLANEOUS 
  37  Multi colour granite coping 20 mm   SQM          0.22
  38  Multi colour granite coping 10 mm   SQM          0.22